Enterprise Customer Owned Utility Tie Subs

See All Projects
Project Details

Completion Date: Completed Over the Last 50+ Years

Location: Houston, TX

  • Multiple 138kV 4 Breaker Ring Bus Substations
  • Includes two (2) Redundant Transformers
  • Typically includes a Control House with a Lineup of MV SWGR for Load Tie Ins
  • Projects are completed on Time Ahead of Utility Outage Dates
  • Ever Changing Utility Specifications are Accounted for in Every Design

Related Projects

2017
Baytown & Mont Belvieu, Texas NAG High Voltage Supply Project

Scope One (1) 138kV 4 Mile Steel Structure Dual Circuit Transmission Line (1) 138kV 4 BKR Ring Substation (2) 138/35kV 80 MVA Power Transformers (1)...

View Project
2020
Centurion Pipeline Midland Project

138/12.47kV Tap Substation Includes two (2) Redundant Transformers Control House with lineup of 12.47kV SWGR 12.47kV Pole Line through the Facility Cutover of New and...

View Project