Completion Date: 2013
Location: Houston, TX
Client: NRG
In late summer 2012, Dashiell accepted a project with an aggressive project schedule to design and build a 138 kV generator interconnect substation and a 138 kV interconnecting transmission line for a new peaking power plant being built by NRG at the W.A. Parish power plant near Richmond, Texas. Although the facilities themselves were not technically difficult to design and build, the number of interfaces between existing NRG facilities, the new peaking power plant and Centerpoint created a number of challenges for the project team.
On Thursday, June 6th, Dashiell successfully energized the interconnect substation bus by re-energizing the transmission line from the Centerpoint substation to the NRG W.A. Parish Unit #7 Standby Transformers. On Friday, June 7th, the interconnect breaker to the new generation facility was closed, energizing the transmission line and back-feeding the new power plant through the Generator Step Up Transformer. Even with all of the interface issues that challenged our energization, Dashiell completed this project a full week ahead of our commitment to the customer.
Dashiell was awarded this project in July, 2020. The substation is an EPC (engineering, procurement, and construction) greenfield project for a 345-138kV substation. The 345kV...
View ProjectEngineering and Construction Services: Four (4) Bays Five (5) Lines Coming In and Out Included Current Limiting Reactors
View ProjectEPC Scopes: (2) – 345kV 3 breaker ring SWYD expandable to a future BAAH (1) – 115kV 3 Bay BAAH SWYD (1) – 115kV 3...
View ProjectAt Dashiell, we recognize that our success begins and ends with our employees and are always on the lookout for new candidates of all experience levels. Apply Today!
Learn MoreOur single source capability allows us to be responsive to our client's needs. Our goal is always the same - to give you a full range of cost-conscious, schedule driven, safe and quality project solutions.
Contact